Chandos Road data-centre development, Park Royal

Planning approvedResearch updated 17 November 2026

Project overview

The planning record identifies a substantive data-centre development at this site.[2]

Who is behind it?

The source identifies VDC LHR12 Ltd in the applicant role for Chandos Road data-centre development, Park Royal.[1]

A future operator or tenant has not been established in the evidence shown here. An applicant or developer is a different role.

At a glance

Current stage
Planning approved
Location
London

Reading the evidence

The current picture

What we know

The planning record identifies a substantive data-centre development at this site.[2]

The authority's published register records this application as Approved. This records the application's status, not construction or operation.[3]

What is proposed

The committee account records proposed vegetable-oil generator fuel.[12]

What remains unclear

Cooling-water consumption is not quantified in the published observations shown here.

The evidence shown here does not establish a current or future operator.

See what has been researched ↓

The local picture

What could it mean locally?

What the available evidence says about jobs, resources and the surrounding area.

Jobs and investment

The authority assessment states: The outline agreement requires an operational-stage local labour and skills strategy, rather than recording actual employment.[7]

Electricity and backup power

The committee account records proposed vegetable-oil generator fuel.[12]

The phase-2 energy assessment estimates six MW of low-grade heat potentially available for a future heat network. This is heat output, not IT power.[13]

Power figures can describe different things: electricity for computing equipment, the whole site or a grid connection. A proposed rating is not a measurement of electricity used.

Water and cooling

The authority assessment states: The drainage strategy includes phase-2 attenuation storage.[22]

Thames Water raised no foul-sewer network-capacity objection in the assessment.[23]

The published observations shown here do not quantify cooling-water consumption. Research coverage below distinguishes checks made from work still outstanding. Drainage and wastewater figures measure different flows.

Environmental effects

The applicant reports improved design-stage on-site carbon savings from 39 to 48 percent.[8]

Officers consider noise and vibration acceptable with suitable construction mitigation; this is a scoped planning assessment.[9]

Community views and consultation

The report records one local-resident objection to the phase-2 application.[5]

The applicant proposes: Members asked officers to verify wind-noise effects; this is a committee question rather than an established adverse impact.[6]

What’s happened so far?

  1. The report dates outline permission to 7 September 2021.[21]

  2. The June 2024 officer report records work starting on phases 1a and 1b; it does not establish phase-2 construction.[20]

Keeping track

What’s next?

A confirmed next decision or construction milestone has not yet been established in this profile. Planning permission alone does not mean building work has started.

Updates follow the evidence. Dates and proposals may change; source dates are retained below.

Documents and detailed evidence

The original records are here for anyone who wants to look more closely. The explanations above are drawn from these observations.

Read the detailed research 24 observations · 3 original sources

Project information

Companies and ownership

[1]applicant

The source identifies VDC LHR12 Ltd in the applicant role for Chandos Road data-centre development, Park Royal.

historic report · Observation date not established
Scope: Chandos Road data-centre development, Park Royal
OPDC · Original project/company role statement

Site and buildings

[14]campus area

The authority assessment states: The outline campus covers 1.86 hectares; phase 2 is smaller.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 1

[15]generator floor area

The authority assessment states: Phase 2 includes an 8,827-square-metre generator building, separate from data-centre floorspace.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

[16]generator height

The authority assessment states: The revision raises the proposed generator building from 22 to 37.25 metres.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

[17]phase two area

The officer report gives 0.74 hectares for the phase-2 site.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 1

[18]phase two floor area

The authority assessment states: Phase 2 includes 16,362 square metres of data-centre space.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

[19]phase two parking

The authority assessment states: The phase-2 scheme includes eleven car-parking spaces.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

Electricity and power

[13]heat reuse design

The phase-2 energy assessment estimates six MW of low-grade heat potentially available for a future heat network. This is heat output, not IT load.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 27

Water and cooling

[22]attenuation

The authority assessment states: The drainage strategy includes phase-2 attenuation storage.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 28

[23]foul network

Thames Water raised no foul-sewer network-capacity objection in the assessment.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 13

[24]surface network

Thames Water raised no surface-water network-capacity objection in the assessment.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 13

Jobs and investment

[7]existing local agreement

The authority assessment states: The outline agreement requires an operational-stage local labour and skills strategy, rather than recording actual employment.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 29

Environmental assessments

[8]carbon savings

The applicant reports improved design-stage on-site carbon savings from 39 to 48 percent.

applicant proposal · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · Project article: carbon-savings

[9]noise assessment

Officers consider noise and vibration acceptable with suitable construction mitigation; this is a scoped planning assessment.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 25

Consultation and concerns

[5]public objection

The report records one local-resident objection to the phase-2 application.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

[6]wind noise question

The applicant proposes: Members asked officers to verify wind-noise effects; this is a committee question rather than an established adverse impact.

applicant proposal · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · Project article: wind-noise-question

Planning applications

[11]phase two revision

The authority assessment states: The phase-2 revision increases its described data-centre capacity from 24 MW to 30 MW; this is a proposal-stage figure.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

Development history

[20]first phase works

The June 2024 officer report records work starting on phases 1a and 1b; it does not establish phase-2 construction.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

[21]outline decision

The report dates outline permission to 7 September 2021.

authority finding · 27 June 2024
Scope: 21/0013/OUTOPDC
OPDC · PDF page 2

Research limits

  • No verified numerical water-demand figure has been found in the documents checked.
  • A future operator or hyperscaler tenant has not been established by the checked sources.
Original documents and source information
Published application location

Greater London Authority / OPDC · Publication date not established

Checked 17 November 2026 · factual-extraction

Application location facts only; original document rights retained. Approximate application area, not a surveyed facility footprint.

Reuse conditions ↗
Planning London Datahub: 21/0013/OUTOPDC

Greater London Authority / OPDC · Publication date not established

Checked 17 November 2026 · factual-extraction

Independently written factual extraction from the cited original. Original copyright and reuse conditions retained; no licence to redistribute source prose, images or documents is asserted.

Reuse conditions ↗
Record information, planning references and field-level evidence

Facility classification

Function and company association are distinct from development status. Categories can overlap.

  • Proposed data-centre development — A development proposal, separately classified from any known facility function and eventual operator. Source
Planning authority
OPDC
Planning reference
21/0013/OUTOPDC
Location accuracy
Approximate application-area centroid published by the GLA; not a surveyed data-centre building footprint.
Record reuse licence
factual-extraction
View field-level evidence (13 claims)

Editorial rules uk-editorial-v2-public-trust-v1 · research version 318. The presentation updates from the underlying evidence. Restricted source text remains private.

What has been researched?

A category review is bounded by the sources checked. It is not an exhaustive search.

Identity
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Site
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Power
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Water
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Employment
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Environment
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Community views and consultation
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
History
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Research updates and corrections

These dated versions record changes to the published research, including corrections and withdrawals. A research update does not establish a change at the site. Earlier source statements and private research remain in the internal evidence history.

  1. 17 November 2026 · 4 observations added; 0 replaced or withdrawn · version 318
  2. 17 November 2026 · 17 observations added; 0 replaced or withdrawn · version 317
  3. 17 November 2026 · First research version · version 164

Something incorrect or missing? Prepare a correction or source suggestion. Reports are checked against the evidence; they do not directly change a published claim.