Project overview

The authority decision records: The Environment Agency granted the original Colt Welwyn installation permit on 18 January 2019.[15]

At a glance

Current stage
Operational
Location
Welwyn Garden City

Reading the evidence

The current picture

What we know

The authority decision records: The Environment Agency granted the original Colt Welwyn installation permit on 18 January 2019.[15]

What is proposed

The applicant proposes: The sheet describes N+1 or N+N standby-generator resilience.[2]

The applicant proposes: Colt specifies 35 MW of IT power for London North.[3]

What remains unclear

Cooling-water consumption is not quantified in the published observations shown here.

The evidence shown here does not establish a current or future operator.

Employment figures are not recorded in the published observations shown here.

See what has been researched ↓

The local picture

What could it mean locally?

What the available evidence says about jobs, resources and the surrounding area.

Electricity and backup power

The applicant proposes: Colt specifies 35 MW of IT power for London North.[3]

The decision recorded 60 generators present in January 2019, with further buildout planned; this is a dated baseline.[16]

Power figures can describe different things: electricity for computing equipment, the whole site or a grid connection. A proposed rating is not a measurement of electricity used.

Water and cooling

The applicant proposes: The sheet specifies N+2 and N+1 cooling-unit resilience.[9]

The applicant proposes: Colt says free cooling is used for most of the year; no numerical water demand is provided.[10]

The published observations shown here do not quantify cooling-water consumption. Research coverage below distinguishes checks made from work still outstanding. Drainage and wastewater figures measure different flows.

Environmental effects

To address modelled short-term nitrogen-dioxide risks, the permit required an air-quality management plan with the local authority.[13]

The authority decision records: The regulator required measurement of actual generator emissions because manufacturer data may not represent reduced-load testing.[14]

Community views and consultation

The 2019 decision records Hertfordshire public-health concerns about local air quality and a request for actual monitoring data.[12]

The county public-health response also requested more information about generator noise under individual testing regimes.[11]

Keeping track

What’s next?

We continue to check for changes to the site and any separate expansion plans. The sources shown here do not establish a confirmed next milestone.

Updates follow the evidence. Dates and proposals may change; source dates are retained below.

Documents and detailed evidence

The original records are here for anyone who wants to look more closely. The explanations above are drawn from these observations.

Read the detailed research 16 observations · 3 original sources

Site and buildings

[8]technical area

The applicant proposes: The published gross technical area is 21,339 square metres.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 2

Electricity and power

[2]generator resilience

The applicant proposes: The sheet describes N+1 or N+N standby-generator resilience.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

[3]it load

The applicant proposes: Colt specifies 35 MW of IT power for London North.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 2

[4]substation 1

The applicant proposes: Substation 1 is specified as 30 MVA at 132 kV; neither figure is IT load.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

[5]substation 2

The applicant proposes: Substation 2 is specified as 30 MVA at 132 kV.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

[6]substation 3

The applicant proposes: Substation 3 is specified as 8 MVA at 11 kV.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

[16]generator count

The decision recorded 60 generators present in January 2019, with further buildout planned; this is a dated baseline.

authority decision · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 2

Water and cooling

[9]cooling resilience

The applicant proposes: The sheet specifies N+2 and N+1 cooling-unit resilience.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

[10]free cooling

The applicant proposes: Colt says free cooling is used for most of the year; no numerical water demand is provided.

applicant proposal · Observation date not established
Scope: Colt London North, Welwyn Garden City
Colt Data Centre Services · PDF page 3

Environmental assessments

[13]air quality management plan

To address modelled short-term nitrogen-dioxide risks, the permit required an air-quality management plan with the local authority.

authority decision · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 4

[14]generator emissions measurement

The authority decision records: The regulator required measurement of actual generator emissions because manufacturer data may not represent reduced-load testing.

authority decision · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 4

Consultation and concerns

[11]county noise information

The county public-health response also requested more information about generator noise under individual testing regimes.

statutory response · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 16

[12]county public health concerns

The 2019 decision records Hertfordshire public-health concerns about local air quality and a request for actual monitoring data.

statutory response · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 16

Planning applications

[15]environmental permit

The authority decision records: The Environment Agency granted the original Colt Welwyn installation permit on 18 January 2019.

authority decision · 18 January 2019
Scope: Colt London North, Welwyn Garden City
Environment Agency · PDF page 1

Research limits

  • No verified numerical water-demand figure has been found in the documents checked.
  • A future operator or hyperscaler tenant has not been established by the checked sources.
Original documents and source information
Record information, planning references and field-level evidence
Planning authority
Welwyn Hatfield
Original project source
SOURCE-e99c73789b9a62a155
Location accuracy
Approximate Welwyn Garden City locality centroid from GeoNames (2634552); not a facility footprint. Original source identifies Welwyn Garden City, Hertfordshire.
Record reuse licence
factual-extraction
View field-level evidence (13 claims)

Editorial rules uk-editorial-v2-public-trust-v1 · research version 329. The presentation updates from the underlying evidence. Restricted source text remains private.

What has been researched?

A category review is bounded by the sources checked. It is not an exhaustive search.

Identity
A bounded search was recorded without a finding. This does not establish that no relevant information or effect exists. Recorded 17 November 2026.
Site
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Power
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Water
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Employment
A bounded search was recorded without a finding. This does not establish that no relevant information or effect exists. Recorded 17 November 2026.
Environment
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Community views and consultation
A bounded search was recorded without a finding. This does not establish that no relevant information or effect exists. Recorded 17 November 2026.
History
Some findings are published. Other questions in this category may still be unresolved. Recorded 17 November 2026.
Research updates and corrections

These dated versions record changes to the published research, including corrections and withdrawals. A research update does not establish a change at the site. Earlier source statements and private research remain in the internal evidence history.

  1. 17 November 2026 · 6 observations added; 0 replaced or withdrawn · version 329
  2. 17 November 2026 · 8 observations added; 0 replaced or withdrawn · version 221
  3. 17 November 2026 · First research version · version 220

Something incorrect or missing? Prepare a correction or source suggestion. Reports are checked against the evidence; they do not directly change a published claim.

Other places nearby

Approximate locations do not establish shared ownership or infrastructure.

Asanti FarnboroughFarnborough · OperationalAsanti ReadingReading · OperationalBroomfield Hospital data centreBroomfield · Planning submitted